#onap-sdnc: CCSDK Weekly 12/15/2017
Meeting started by djtimoney at 16:06:21 UTC
(full logs).
Meeting summary
- Beijing release contents (djtimoney, 16:08:13)
- Priority for Beijing release is platform
maturity. Specific criteria and our commitments can be found in
CCSDK Beijing release planning template :
https://wiki.onap.org/display/DW/Release+Planning+Template+%3A+CCSDK+Beijing+Release
(djtimoney,
17:03:24)
- Functional requirements for Beijing release
also presented at ONAP developer event :
https://wiki.onap.org/download/attachments/20086968/ONAP%20Beijing%20functional%20requirements%20from%20usecase%20subcommittee%20r2.xlsx?api=v2
(djtimoney,
17:04:45)
- More detail to come on functional
requirements (djtimoney,
17:05:04)
- Jira filter defined listing current CCSDK
epics/user stories for Beijing release :
https://jira.onap.org/browse/CCSDK-152?filter=10792 (djtimoney,
17:06:32)
- Beijing release schedule (djtimoney, 17:06:59)
- Reviewed Beijing release schedule presented at
ONAP developer event :
https://wiki.onap.org/download/attachments/3246393/ONAP-BeijingCalendarDevelopmentBestPracticesV2.pdf?version=1&modificationDate=1513102092000&api=v2
(djtimoney,
17:08:10)
- Dan noted that dates on schedule reflect dates
of TSC review/approval of milestone. Milestone deliverables
themselves must be completed 3 days earlier to permit time for
review. (djtimoney,
17:09:08)
- Release planning templates for Beijing are due
1/8 - 10 days prior to M1 milestone date. By that date, all epics
for Beijing must be defined. (djtimoney,
17:09:54)
- Beijing assignments (djtimoney, 17:10:07)
- Dan is reviewing Epics/User stories to verify
that user stories can fit in single sprint. Will create initial
sprints for Beijing and ask for volunteers via onap-discuss mailing
list. (djtimoney,
17:10:58)
Meeting ended at 17:11:22 UTC