============================================================================ #opnfv-meeting: Second Arno adjusted target release plan planning meeting :D ============================================================================ Meeting started by ChrisPriceAB at 07:01:49 UTC. The full logs are available at http://ircbot.wl.linuxfoundation.org/meetings/opnfv-meeting/2015/opnfv-meeting.2015-04-23-07.01.log.html . Meeting summary --------------- * roll call (ChrisPriceAB, 07:01:55) * Uli (ulik, 07:02:06) * Release readiness update (ChrisPriceAB, 07:04:07) * LINK: https://wiki.opnfv.org/releases/arno/releasereadiness release readiness task list (ChrisPriceAB, 07:04:25) * we discussed last night beginning to put dependancies in this task list, I also had an action to update the opnfvdocs pieces. (ChrisPriceAB, 07:04:49) * these did not start last night after the meeting, we can do so today. (ChrisPriceAB, 07:05:03) * we agreed to use "themes" as a way or organising activities into dependancies, rather than trying ot use the numbered list. (ChrisPriceAB, 07:05:36) * Frank Brockners (frankbrockners, 07:05:54) * we also agreed to provide some project planning on the wiki and develop that during today. (ChrisPriceAB, 07:06:14) * Themes = high-level categories/groups (frankbrockners, 07:06:29) * have a look at the wiki (frankbrockners, 07:06:39) * The themes we to be idetifyable activities that might contain sub-tasks that are easily refferable as depenadancies on the other items (like a story) (ChrisPriceAB, 07:07:03) * first column is the category - things that naturally belong together (frankbrockners, 07:07:08) * a theme is like SYS.READY which requires all system readiness activities to be complete prior to the theme itself being ready (ChrisPriceAB, 07:07:40) * we additional articulated the task dependancy that forms the process required to achieve Arno completion (ChrisPriceAB, 07:08:48) * Time to release readiness: max{TEST.READY, SYS.READY} + max{SYS.AUTOMATED,TEST.EXEC} + SYS.RELEASE + DOCS.READY (ChrisPriceAB, 07:08:51) * this provides us with a way of combining tasks and pending time into an equation that gives an indicative release date (ChrisPriceAB, 07:09:26) * we still have not begun to work with functest, morgan is back in the office today. (ChrisPriceAB, 07:10:42) * and there are themes/categories which have an "unknown" time for now - true for SYS.RELEASE, SYS.READY and TEST.READY (frankbrockners, 07:11:33) * in parallel jose_lausuch will work on Tempest automation, pbandzi will work on robot automation, the app deploy teams are working in parallel. (ChrisPriceAB, 07:11:38) * no timelines have been developed for these activities yet. (ChrisPriceAB, 07:11:50) * ACTION: all project leads to ensure we have time estimates for remaining tasks and that the dependancies are defined on other tasks (ChrisPriceAB, 07:12:45) * this will provide a method of estimating parallelism and the critical path for the remaining project activities (ChrisPriceAB, 07:13:11) * we need to work in parallel on the WiKi during the day and will agree between the project leads on the final pre-TSC meeting today on the proposed plan (ChrisPriceAB, 07:14:28) * activities to be completed prior to Final pre-TSC Arno planning meeting. (ChrisPriceAB, 07:20:31) * fill in column 7 (dependancies) where needed to be drawn out (ChrisPriceAB, 07:21:05) * fill in column 6 (time to completion) with estimates on task completion timelines (ChrisPriceAB, 07:21:27) * only add dependancies were there cannot be parallelism (that includes resources) (ChrisPriceAB, 07:21:50) * for tasks "almost complete" where we will be troubleshooting when a dependant task tries to use it, it may be better to dfactor that cost in to the dependant task. opinions? (ChrisPriceAB, 07:22:39) * ACTION: functest team to complete the project with best known estimates (ChrisPriceAB, 07:23:28) * ACTION: opnfvdocs team to compete actions outlined in the previous meeting (ChrisPriceAB, 07:23:45) * ACTION: PL's to work on the project plan text on the wiki. We can add a description of our tasks in simple language there which we can edit after lunch today into a singular Arno text (ChrisPriceAB, 07:24:39) Meeting ended at 07:26:52 UTC. People present (lines said) --------------------------- * ChrisPriceAB (51) * ulik (14) * frankbrockners (11) * collabot (3) Generated by `MeetBot`_ 0.1.4