#fdio-csit: 28-Feb FD.io CSIT Project Meeting
Meeting started by mackonstan at 14:58:57 UTC
(full logs).
Meeting summary
- agenda bashing (mackonstan, 14:59:08)
- Dave Wallace (dwallace_,
15:00:30)
- Tibor Frank (tifrank,
15:01:14)
- Jan Gelety (jgelety,
15:01:51)
- Marek Gradzki (mgradzki,
15:02:58)
- Peter Mikus (pmikus1,
15:03:13)
- VPP (mackonstan, 15:06:10)
- rolling along with 18.04 (mackonstan,
15:06:25)
- HC (mackonstan, 15:06:32)
- Marek - ACLplugin tests are failing, most
likely environment, root causing (mackonstan,
15:06:59)
- Tom Herbert (tfherbert,
15:07:09)
- Operational status (mackonstan, 15:08:10)
- Peter - issue affecting Centos, can't start
VIRL simulations with latest VPP pkgs (mackonstan,
15:08:36)
- ^ I am signed up for Infra/CICD meeting.
(tfherbert,
15:08:45)
- Peter - need to speedup new Centos image
preparation as there is new dependency in VPP on selinux package.Due
to this missing package dependency package we are not able to use
latest VPP version (mackonstan,
15:09:05)
- this is due to selinux dependency (mackonstan,
15:09:28)
- rls1801 regressions (mackonstan, 15:23:47)
- CSIT-927 - rls1801 substantial NDR performance
regression for vhost-user vring size of 1024 - fixed CSIT
code (mackonstan,
15:25:23)
- CSIT-925 plugin bisecting - Jan updating - git
bisecting progress made.. showed xls data - summary lateron in email
/ vpp-dev call next week (mackonstan,
16:00:23)
- CSIT-925 plugin bisecting - Jan updating -
plugin bisecting progress made.. showed xls data - identified a set
of 6 suspected plugins (mackonstan,
16:02:24)
- CSIT-926 git commit-id bisecting - Jan updating
- identified few patches responsible for degradation - summary later
on in email / vpp-dev call next week (mackonstan,
16:02:55)
Meeting ended at 16:05:27 UTC
(full logs).
Action items
- (none)
People present (lines said)
- mackonstan (17)
- collabot` (4)
- tfherbert (2)
- mgradzki (1)
- jgelety (1)
- dwallace_ (1)
- pmikus1 (1)
- tifrank (1)
Generated by MeetBot 0.1.4.