#fdio-csit: FD.io CSIT project meeting
Meeting started by mackonstan at 14:01:41 UTC
(full logs).
Meeting summary
-
- Jan Gelety (jgelety,
14:01:47)
- Juraj Linkeš (jlinkes,
14:01:54)
- Peter Mikus (pmikus,
14:01:55)
- Vratko Polak (vrpolak,
14:01:59)
- Agenda bashing (mackonstan, 14:03:45)
- Inputs from LFN and FD.io projects (mackonstan, 14:05:10)
- VPP - API freeze in 2 weeks time (mackonstan,
14:07:58)
- HoneyComb - Michal updating - CSIT tests still
failing, work in progress, have line of sight (mackonstan,
14:08:30)
- CSIT operational status (mackonstan, 14:09:15)
- move from nexus to packagecloud.io went
smoothly (mackonstan,
14:10:52)
- issue with jjb not being verified - helpdesk
ticket by Tibor (mackonstan,
14:11:36)
- ci-management-verify-jjb is failing: FD.io
Helpdesk #61074 (pmikus,
14:13:02)
- make test issues resolved.. but bionic make
tests are failing (mackonstan,
14:13:11)
- Juraj - still some hiccups on Arm, tests
executed properly, but many tests are failing (mackonstan,
14:14:21)
- VPP code performance (mackonstan, 14:14:54)
- many tests are failing for a while now mainly
link bonding (mackonstan,
14:16:56)
- suspected root cause is interface up/down api
issue vpp-1361 based on Peter's logs pointing to DPDK driver
issue (mackonstan,
14:18:30)
- Maciek to contact Ray and get advice how to
drive the resolution (mackonstan,
14:19:15)
- https://docs.fd.io/csit/master/trending/introduction/failures.html#n-hsw
(mackonstan,
14:19:27)
- https://docs.fd.io/csit/master/trending/introduction/failures.html#n-skx
(mackonstan,
14:19:37)
- https://docs.fd.io/csit/master/trending/introduction/failures.html#id1
(mackonstan,
14:20:05)
- some degradation for l3fwd (mackonstan,
14:22:53)
- red cases require investigation (mackonstan,
14:23:17)
- Alerting to csit-report] almost done by Tibor,
will send template email for review to csit-dev (mackonstan,
14:25:35)
- and to vpp-dev (mackonstan,
14:25:47)
- CSIT Releases (mackonstan, 14:26:05)
- CSIT-18.07 known issues updates (mackonstan,
14:26:42)
- VPP-1361 logs with DPDK guys (mackonstan,
14:27:01)
- CSIT-1266 and CSIT-1267 issues fixed.
(mackonstan,
14:28:45)
- CSIT-1266 data can be easily refreshed in next
rev of CSIT-18.07 report (mackonstan,
14:31:01)
- CSIT-1267 requires more care, Tibor will
analyse possible options (mackonstan,
14:31:47)
- likely to require using database instead of
Nexus (mackonstan,
14:34:21)
- Tibor to look at dbase choices (relational?)
and then we can test waters with LF (mackonstan,
14:35:55)
- CSIT-18.10 plan (mackonstan,
14:37:53)
- Matus will link jira epics to wiki (mackonstan,
14:38:03)
- https://wiki.fd.io/view/CSIT/csit1810_plan
(mackonstan,
14:38:13)
- CSIT-18.10 F0 in 2 weeks time (mackonstan,
14:38:55)
- New test environments (mackonstan, 14:41:13)
- VPP_Device 1-Node - Peter provided summary,
next TWS call tomorrow (mackonstan,
14:41:53)
- VPP_Path: CSIT_VIRL migration progress - no
update (mackonstan,
14:45:32)
- VPP_Path_Device: tests for new 2-Node Skx - Jan
making very good progress, most of them are in trending as matching
existing tags (mackonstan,
14:46:09)
- tests with new tags would need to be coded into
PAL trending (mackonstan,
14:46:27)
- VPP_Path_Device: tests for new Arm - Juraj
updating - Huawei taischan - kamendra kumar driving this work,
encountering some issues (mackonstan,
14:48:42)
- khemendra kumar (mackonstan,
14:50:55)
- Analytics: Per VPP patch vs. parent - Vratko -
collecting data, number of false positives, waiting till next week
for enough data to analyze and decide on next steps (mackonstan,
14:52:20)
- PAL: Performance trending - Vratko - moved to
10x1sec BMRR tests. time to ask PAL to look at stdev for increased
detection precision (mackonstan,
14:54:23)
- PAL: adding "vpp show run" - Ole Troan
confirmed that vpp stats infra is ready for prime time, still
working on show run equivalent conteint (mackonstan,
14:55:56)
- VAT to PAPI - time for (more than) baby steps
in CSIT-18.10.. (mackonstan,
14:56:11)
- VAT to PAPI - time for (more than) baby steps in CSIT-18.10.. (mackonstan, 14:56:20)
- Peter working on proposal (mackonstan,
14:58:21)
- TRex (mackonstan, 14:58:53)
- no update (mackonstan,
14:58:57)
- New FD.io CSIT lab - Xeons, Arm, Atom (mackonstan, 14:59:19)
- All Xeon motherboard RMAs arrived, to be
installed (mackonstan,
14:59:52)
- LF IT / Anton proceeding with install with
Peter supervision (mackonstan,
15:00:17)
- bios upgrade on Xeon 1-node as no NICs
seen (mackonstan,
15:00:29)
Meeting ended at 16:00:03 UTC
(full logs).
Action items
- (none)
People present (lines said)
- mackonstan (56)
- collabot (4)
- pmikus (2)
- vrpolak (1)
- jgelety (1)
- jlinkes (1)
Generated by MeetBot 0.1.4.