    1. Tibor Frank (tifrank, 14:02:00)
    2. Jan Gelety (jgelety, 14:02:14)
    3. Dave Wallace (dwallacelf, 14:02:14)
    4. Tom Herbert (tfherbert, 14:02:20)
    5. Vratko Polak. (vrpolak, 14:02:55)

  1. Agenda bashing (mackonstan, 14:03:54)
  2. FD.io CSIT lab infrastructure - skipping (mackonstan, 14:04:13)
    1. Juraj Linkeš (jlinkes, 14:04:21)
    2. Maciek: final BOM for LFN FD.io 2019 lab extension provided - will send summary to csit-dev mailer. (mackonstan, 14:05:33)

  3. Inputs from LFN and FD.io projects (mackonstan, 14:06:16)
    1. Dave: added standing agenda item to go over any upcoming VPP API changes (mackonstan, 14:06:37)

  4. Operational status (mackonstan, 14:08:19)
    1. Peter Mikus (pmikus, 14:08:40)
    2. Number of trending jobs keep failing due to FIB API incompatibility after VPP API change (mackonstan, 14:10:47)
    3. Tibor: didn't see any issues since last week, issue went away "silently" (mackonstan, 14:12:49)
    4. Ed: LFN IT team rebooted Jenkins to work around the load/slowness related issue (mackonstan, 14:13:34)
    5. see email from Vanessa re additional loggign and Jenkins maintenance on 02-July (mackonstan, 14:14:08)
    6. Centos CI: Tom reporting - sent email re Nomad execution, waiting for someone (Ed?) to pick up, will resend email (mackonstan, 14:15:07)
    7. Ed: should be easy to resolve (mackonstan, 14:16:39)

  5. VPP code performance (mackonstan, 14:16:40)
    1. Jan: fixing IP FIB API that should solve the incompatibility with VPP after their change (mackonstan, 14:18:39)
    2. https://gerrit.fd.io/r/c/20278/ (mackonstan, 14:18:42)
    3. Jan: all tests done, ready for merge, need review(s) (mackonstan, 14:19:40)

  6. Releases (mackonstan, 14:20:12)
    1. CSIT-1908 plan (mackonstan, 14:21:58)
    2. https://wiki.fd.io/view/CSIT/csit1908_plan (mackonstan, 14:22:14)

  7. Developments (mackonstan, 14:23:04)
  8. Framework - VAT to PAPI migration (mackonstan, 14:24:12)
    1. L1 KW refactoring VAT to PAPI - Tibor: all what planned for June is done and merged. Added three more. (mackonstan, 14:25:08)
    2. L1 KW refactoring VAT to PAPI - Jan: finished IPUtil, going back to IPsec, then next SRv6 libraries. (mackonstan, 14:25:46)
    3. Jan: issues with PAPI for scale tests - lots of entries in PAPI history, quick fix is to print just first two lines and last two lines for all scale tests (for MAC, IPv4, IPv6); (mackonstan, 14:30:12)
    4. Jan: separate issue is the actual logging of cmds - several times - need fix. Proposal over email. (mackonstan, 14:34:22)
    5. Vratko: PAPI over remote socket improves PAPI performance, but still not fast enough due to synchronous operation 1k commands/sec (mackonstan, 14:36:02)
    6. Vratko: solution is asynchronous operation, this needs some thinking (mackonstan, 14:36:33)
    7. Vratko: PAPI over remote socket - conflict with msg indeces; doesn't happen w/o remote socket (mackonstan, 14:39:21)
    8. Vratko: suspecting issue/bug in VPP (mackonstan, 14:39:36)
    9. https://jenkins.fd.io/view/csit/job/csit-vpp-perf-mrr-daily-master-3n-skx/496/ showing info_level logs increased to 1.13G for 227TCs (pmikus, 14:39:38)

  9. Framework -  L1 KWs alignment between dev and perf (mackonstan, 14:40:15)
    1. Peter: progressing well for setup and teardown (mackonstan, 14:40:31)
    2. Peter: some tests working, some more cleanup required (mackonstan, 14:40:45)

  10. VPP-API "Flag Day" - CSIT-VPP gate-keeping (mackonstan, 14:41:19)
    1. Dave: Vratko is refactoring original implementation to adapt to remote socket (mackonstan, 14:42:08)
    2. Alignment of DEV/PERF was split to 3 phases. 1) Teardown -done, 2) Setup phase -done, 3) Configuration -in progress. 3rd part should be final for the ready-to-go solution (pmikus, 14:42:37)
    3. Discussion: how to integrate this into vpp-csit- jobs - new job to be run first and stop other jobs, similar to checkstyle jobs (mackonstan, 14:49:23)

  11. Test environments (mackonstan, 14:49:57)
  12. Performance trending and analytics (mackonstan, 14:50:41)
  13. New tests (mackonstan, 14:50:46)
    1. Vratko: 9000B tests for AVF got added via suite generator change, based on VPP doc change (mackonstan, 14:51:51)

  14. TRex (mackonstan, 14:52:48)
    1. Latency HdrHistogram - code aligned with latest TRex master, but no target rls confirmed yet (mackonstan, 14:53:19)
    2. Swati: joined Cisco recently, part of FD.io release engineering team (mackonstan, 14:54:19)


Meeting ended at 14:57:07 UTC (full logs).

Action items

  1. (none)


People present (lines said)

  1. mackonstan (45)
  2. collabot` (4)
  3. pmikus (3)
  4. vrpolak (1)
  5. jlinkes (1)
  6. jgelety (1)
  7. dwallacelf (1)
  8. tfherbert (1)
  9. tifrank (1)


Generated by MeetBot 0.1.4.