#onap-int: integration weekly meeting 27/02/2018

Meeting started by morgan_orange at 14:31:41 UTC (full logs).

Meeting summary

  1. action points follow up (morgan_orange, 14:35:08)
    1. AP1: morgan_orange synch with Eric on INT-340 (morgan_orange, 14:35:16)
    2. study to reduce the size of ONAP (light configuration) done by E.Debeau (morgan_orange, 14:35:58)
    3. without considering DCAE (morgan_orange, 14:36:08)
    4. most of the VMs can be significantly reduced and ONAP keep on running (in a minimal config) (morgan_orange, 14:36:08)
    5. e.g. dns large => small (14 to 1 vCPU) (morgan_orange, 14:36:08)
    6. aai1: xlarge => large (14 to 4 vCPU) (morgan_orange, 14:36:08)
    7. overall (without DCAE): from 208 vCPU to 37 (morgan_orange, 14:36:08)
    8. I suggest to create a page to mention the different values (morgan_orange, 14:36:08)
    9. ACTION: eric create a heat-minimum config in the integration repo (morgan_orange, 14:36:58)
    10. https://git.onap.org/demo/tree/heat/ONAP (morgan_orange, 14:37:36)
    11. AP2: helenychen follow-up with mickael on INT-300 and INT-346 (morgan_orange, 14:37:52)
    12. done (morgan_orange, 14:37:58)
    13. AP4: helenychen follow up on tag mechanism INT-189 (morgan_orange, 14:38:06)
    14. gildaslanilis mentions that there is work in progress on the standardization of the tagging (morgan_orange, 14:40:40)
    15. LF will tag the images as described in the wiki (morgan_orange, 14:40:53)
    16. https://wiki.onap.org/display/DW/Independent+Versioning+and+Release+Process#IndependentVersioningandReleaseProcess-StandardizedDockerTagging (morgan_orange, 14:41:39)
    17. https://jira.onap.org/browse/CIMAN-132 (morgan_orange, 14:43:17)
    18. work consisting in creating INFO in repo to manage users in progress (morgan_orange, 14:43:51)
    19. trial in progress with some projects (morgan_orange, 14:44:04)
    20. done (morgan_orange, 14:44:28)
    21. AP5 helenychen follow up with Edmund Haselwanter on INT-292 (morgan_orange, 14:44:35)

  2. Stabilize Master branch? (morgan_orange, 14:44:51)
    1. ONAP Beijing release cannot currently deploy; question is when we need the project teams to stabilize the deployments (gwu, 14:47:49)
    2. concern on the latest build: CI chain needed to give confidence on the integration (morgan_orange, 14:48:12)
    3. 2 chains needed amsterdam (stable) and master (Beijing) (morgan_orange, 14:48:26)
    4. lots of changes in master at the moment... (morgan_orange, 14:50:55)
    5. components csit currently failing. minimum for M3 would be that the csit tests are OK (morgan_orange, 14:52:08)
    6. ACTION: gildaslanilis follow-up with dmaap => csit tests down since 3 months... (morgan_orange, 14:53:23)

  3. S3P Testing Tools progress (morgan_orange, 14:54:20)
    1. internal syncho integration meeting on tooling (advantages/drawbacks) + demo on Locust (morgan_orange, 14:55:04)
    2. JMeter great tool but complex to manage and adapt to integration context (morgan_orange, 14:56:16)
    3. ran indicates that Locust is much easier to manage especially for end users (morgan_orange, 14:56:40)
    4. ACTION: ran plan a demo for the meeting next week (morgan_orange, 14:58:05)
    5. helenychen "S3P testing is key for Beijing" (morgan_orange, 14:59:17)
    6. ACTION: Luman plan a demo on JProfile 13th of March (morgan_orange, 15:04:33)
    7. Luman no access to windriver lab so far (morgan_orange, 15:04:55)
    8. ACTION: helenychen follow up China Mobile access to windriver lab (morgan_orange, 15:05:09)
    9. ACTION: george nmap demo to be planned (Connectivy issues with integration lab) (morgan_orange, 15:08:35)
    10. question on the flow matrix (ports) nmap is scanning stuff...so it would be interesting what should eb open or npot (morgan_orange, 15:08:55)

  4. Going through Integration M3 Sprint (morgan_orange, 15:16:12)
    1. https://jira.onap.org/secure/RapidBoard.jspa?rapidView=81&view=planning.nodetail (morgan_orange, 15:16:22)
    2. new use case based on vLB & vDNS in progress (with manaul scaling) (morgan_orange, 15:18:44)

  5. Follow up (morgan_orange, 15:43:21)
    1. http://testresults.opnfv.org/onap-testing/ (morgan_orange, 15:43:23)
    2. morgan_orange reminds that the request for resources has been sent more than 1 month ago (morgan_orange, 16:15:32)
    3. morgan_orange the code shall speak, it can be criticisez, commented, refused but it shall be code centric and not meeting centric (morgan_orange, 16:16:05)
    4. helenychen mentioned that some (shy) people are not convinced by the approach (morgan_orange, 16:16:27)
    5. typically these people shall express themselves though teh code review not from meeting statement (morgan_orange, 16:17:21)
    6. helenychen would like a conf between functest and jenkins (morgan_orange, 16:17:32)
    7. morgan_orange explains that it has no sense: jenkins = gitlab = tool to send jobs in CI (morgan_orange, 16:17:51)
    8. functest is just a simple framework to run tests (framework, python, bash based ..) in a consistent way. The developers has not to take care of the jenkins, the test results reporting. Functest provides some guidelines so the results, the cases, the projects are consistant accross the diferent projects (morgan_orange, 16:19:32)
    9. bitergia has developed some code to extract some info from the DB and create a dedicated testing dashboard in OPNFV (morgan_orange, 16:20:45)
    10. https://opnfv.biterg.io/app/kibana#/dashboard/Testing (morgan_orange, 16:21:12)
    11. functest is not the only option, it is only one way to create a consistent view. It can coexist with other otpions, but there is no reason to prevent comitting.. (morgan_orange, 16:22:43)
    12. hot discussion on who decides what is useful or not in an Open Source community (morgan_orange, 16:22:58)
    13. morgan_orange mentioned that the Open Source way is different from the top/down traditional approach. Tha adoption is based on the code and the community not on meeting decisions (morgan_orange, 16:23:47)
    14. current status of daily tests on Orange open lab (Amsterdam MR installed with heat triggered using internal gitlab) of the main healthcheck tests http://testresults.opnfv.org/onap-testing/amsterdam/functest/status-heat.html (morgan_orange, 16:25:21)

  6. AoB (morgan_orange, 16:25:40)


Meeting ended at 16:25:43 UTC (full logs).

Action items

  1. eric create a heat-minimum config in the integration repo
  2. gildaslanilis follow-up with dmaap => csit tests down since 3 months...
  3. ran plan a demo for the meeting next week
  4. Luman plan a demo on JProfile 13th of March
  5. helenychen follow up China Mobile access to windriver lab
  6. george nmap demo to be planned (Connectivy issues with integration lab)


Action items, by person

  1. gildaslanilis
    1. gildaslanilis follow-up with dmaap => csit tests down since 3 months...
  2. helenychen
    1. helenychen follow up China Mobile access to windriver lab
  3. UNASSIGNED
    1. eric create a heat-minimum config in the integration repo
    2. ran plan a demo for the meeting next week
    3. Luman plan a demo on JProfile 13th of March
    4. george nmap demo to be planned (Connectivy issues with integration lab)


People present (lines said)

  1. morgan_orange (76)
  2. collabot` (10)
  3. gwu (3)
  4. ntpttr (0)
  5. electrocucaracha (0)
  6. helenychen (0)
  7. kennypaul (0)
  8. gildaslanilis (0)
  9. csatari (0)


Generated by MeetBot 0.1.4.