- Arun from VMWare reports that k8s v4.1 will
be installed in OpenLab (Yang__,
14:05:20)
- Arun is also working on OOF testing
(Yang__,
14:07:32)
- Gary says 30/34 out HEAT, 22/34 out of OOM
sanity test (Yang__,
14:09:08)
- passed sanity test (Yang__,
14:09:47)
- Gary: Dash board reports cover WindRiver and
TLab (Yang__,
14:11:44)
- Gary: The dashboard reports are aggregated of
the two labs, will separate them in the future (Yang__,
14:12:56)
- Nexus3 is slow lately on image download, will
have meeting later on the issue (Yang__,
14:14:17)
- Marco: MUSIC HEAT installation is done, working
on OOF HEAT installation (Yang__,
14:16:54)
- Marco: also working on AAF HEAT
installation (Yang__,
14:18:30)
- Marco: Waiting for AAF team to provide
certificate info for installation, will have working session with
AAF team (Yang__,
14:25:42)
- Brian will look at vFW/vLB automation change
done in Amsterdam, and do cherry-pick (Yang__,
14:30:12)
- Chengli CMCC lab will test HPA feature with
vCPE (Yang__,
14:35:06)
- Helen: will verify that HPA feature can be
tested in Intel lab (Yang__,
14:35:50)
- Brian: shared the pairwise test status. HEAT
pairwise test is doing ok, but OOM pairwise test very few has
done (Yang__,
14:41:49)
- Brian shared integration.yaml and helm
cheatsheet (Yang__,
14:53:18)
- Roger: project teams are late on OOM and
HEAT (Yang__,
15:02:43)
- Brian: suggest to ask Gildas to push RC0 by a
week (Yang__,
15:04:46)
Meeting ended at 15:31:20 UTC