#onap-int: Integration weekly meeting
Meeting started by helenychen at 14:01:17 UTC
(full logs).
Meeting summary
-
- possible additional topics on 5G, test
automation, best practice to build containers (next week)
(morgan_orange,
14:04:38)
- http://ircbot.wl.linuxfoundation.org/meetings/onap-int/2018/onap-int.2018-08-15-14.03.html
(morgan_orange,
14:05:25)
- AP1: Andrew to schedule a separate
meeting/discussion on test VNFs (morgan_orange,
14:05:58)
- mail thread in progress (morgan_orange,
14:06:16)
- meeting to be planned (morgan_orange,
14:06:36)
- ACTION: Andrew to
schedule a separate meeting/discussion on test VNFs (morgan_orange,
14:06:37)
- AP2: Kang to follow up on vCPE
automation (morgan_orange,
14:06:46)
- progress on the use case, still some work on
automation (morgan_orange,
14:07:53)
- helenychen suggests that China Mobile could try
to run vCPE testcase in open labs to get a larger feedback
(morgan_orange,
14:10:51)
- Yang mentions possible problem with VNF
licensing (morgan_orange,
14:11:13)
- ACTION: Yang
follow-up vCPE / VoLTE use case with China Mobile (morgan_orange,
14:12:07)
- additional infos exepcted on VNF strategy in
the lab (proprietary / Open Source) => test cases shall be fully
defined for M3 milestones planned soon (morgan_orange,
14:13:45)
- helenychen asks for visibility on 5G use
case (morgan_orange,
14:14:13)
- https://wiki.onap.org/display/DW/5G+-+Real+Time+PM+and+High+Volume+Stream+Data+Collection+-+Integration+Test+Cases
(morgan_orange,
14:17:27)
- question on where the code of the PNF simulator
will be located: demo? (morgan_orange,
14:18:14)
- it will be in an ONAP repo (morgan_orange,
14:18:52)
- ACTION: Krysztof
clarify where the code will be hosted and possibly details on open
meetings on the topic (morgan_orange,
14:19:32)
- https://wiki.onap.org/display/DW/5G+-+PNF+PnP+-+Integration+Test+Cases
(morgan_orange,
14:22:10)
- current testing in progress internally on
theses 5G cases on top of Beijing solution. Problem with SO.
(morgan_orange,
14:24:23)
- open questions on the deadline? (morgan_orange,
14:27:12)
- M3 is planned tomorrow (morgan_orange,
14:27:17)
- M4: mid of September (morgan_orange,
14:28:33)
- question on the target test environment
(morgan_orange,
14:28:58)
- 5G team looking for place (morgan_orange,
14:31:45)
- ACTION: Krysztof
contact morgan_orange to discuss access ot Orange lab (use case
expected for Casablanca - Casablanca version is needed) (morgan_orange,
14:34:13)
- other candidate is TLab (pretty stable) and
windriver (morgan_orange,
14:34:30)
- 5G needs resources after M4 (morgan_orange,
14:34:50)
- Brian expects some min robot integration
(sunnyday flows) (morgan_orange,
14:39:12)
- ACTION: helenychen
follow-up on early robot min integration (morgan_orange,
14:40:57)
- such tests are the step after healthcheck
(docker OK) (morgan_orange,
14:43:02)
- https://git.onap.org/testsuite/tree/robot/testsuites
(morgan_orange,
14:43:15)
- ACTION: Brian plan a
short introduction to Robot within ONAP context for next integration
weekly meeting (morgan_orange,
14:44:13)
- upgrade to Pike on windriver lab triggered some
instabilities (problably still some side effects still to be
planned) (morgan_orange,
14:46:47)
- Happy Birthday Gary! (morgan_orange,
14:47:03)
- target using OOM after M4 (currently heat still
currently used) (morgan_orange,
14:48:16)
- discussion on OOM refactoring status - lots
open questions (morgan_orange,
14:50:35)
- question on the integration of a security test
suite (morgan_orange,
14:52:10)
- question if it planned to use nessus to scan
vulnerability (morgan_orange,
14:53:39)
- CIA update: adolfo gives a status of best
practices (will be integrated in the read the doc) (morgan_orange,
14:55:28)
- some docs have been shared with the community
for review (morgan_orange,
14:55:51)
- helenychen asks if adolfo wants to report
progress during PTLs ' meeting (morgan_orange,
14:58:32)
- adolfo suggests a demo: move from a big to a
small image... (morgan_orange,
14:59:16)
- helenychen suggests to extend integration
meeting to share the demo (morgan_orange,
15:00:01)
- benchmark update: resiliency 80%, perfo: 20%,
stability: 20%, scalability: 20% (morgan_orange,
15:01:48)
- ONAP env not available last week => delay on
benchmark work (morgan_orange,
15:02:07)
- vCPE automation - to be rescheduled
(morgan_orange,
15:03:27)
Meeting ended at 15:08:01 UTC
(full logs).
Action items
- Andrew to schedule a separate meeting/discussion on test VNFs
- Yang follow-up vCPE / VoLTE use case with China Mobile
- Krysztof clarify where the code will be hosted and possibly details on open meetings on the topic
- Krysztof contact morgan_orange to discuss access ot Orange lab (use case expected for Casablanca - Casablanca version is needed)
- helenychen follow-up on early robot min integration
- Brian plan a short introduction to Robot within ONAP context for next integration weekly meeting
Action items, by person
- helenychen
- helenychen follow-up on early robot min integration
- morgan_orange
- Krysztof contact morgan_orange to discuss access ot Orange lab (use case expected for Casablanca - Casablanca version is needed)
- UNASSIGNED
- Andrew to schedule a separate meeting/discussion on test VNFs
- Yang follow-up vCPE / VoLTE use case with China Mobile
- Krysztof clarify where the code will be hosted and possibly details on open meetings on the topic
- Brian plan a short introduction to Robot within ONAP context for next integration weekly meeting
People present (lines said)