Meeting started by gwu at 13:08:29 UTC (full logs).

Meeting summary

  1. review of last week (gwu, 13:08:48)
    1. passed M3 review (gwu, 13:08:57)
    2. oparent 1.2.3 released (gwu, 13:09:25)
    3. correction: passed M3 archcom review; M3 review is upcoming (gwu, 13:10:03)
    4. merging of docker manifests into OOM under ongoing discussions with OOM team (gwu, 13:12:05)
    5. discussions on renabling oom-staging-daily deployment tests (gwu, 13:15:41)
    6. shortage of resources: 4 instances available on windriver lab: 2 for Casablanca, 1 for stagging and 1 for Dublin (morgan_orange, 13:18:20)
    7. review last week's action items (gwu, 13:19:48)
    8. Gary proposal shared with OOM team, no consensus reached yet, work/discussion still in progress (morgan_orange, 13:20:30)

  2. Dublin blocking issues (gwu, 13:20:47)
    1. https://wiki.onap.org/display/DW/Dublin+Release+Integration+Test+Blocking+Issues (morgan_orange, 13:21:07)
    2. 3 blocking points (2 for the VID/Portal) and 1 for SO (SO-1617) (morgan_orange, 13:22:09)
    3. Yang indicates that for the troubleshooting of VID issue is relatively slow, bug open 1 week ago but root cause still not clear (morgan_orange, 13:25:07)
    4. VID issue probably linked to AAI bugs (AAI-2222) => gerrit 79705 should fix the problem but patch not merged in OOM (morgan_orange, 13:28:33)
    5. Yang suggested 1 topic on pair wise testing / best practice installation/troubleshooting/how to write the robot test cases (morgan_orange, 13:33:00)
    6. Yang will focus on installation/Gary's script/troubleshooting and Brian and Robot part (morgan_orange, 13:35:16)
    7. https://wiki.onap.org/display/DW/Project+Status+in+Dublin+Release (morgan_orange, 13:37:14)
    8. SNIRO emulator jenkins build failed (morgan_orange, 13:38:15)
    9. Dmitry indictaes that nothing changed for a while => transient error? re run the job to check? (morgan_orange, 13:39:04)
    10. sniroemeulator is in integration repo (morgan_orange, 13:41:22)
    11. morgan_orange mentions that the docker has not been built for a long time (9 months > 1 release window time) => woudl make sense to rebuilt it (fix security vulnaribilities from underlay OS used to build the docker) (morgan_orange, 13:42:24)
    12. https://wiki.onap.org/display/DW/Reduction+effort+between+Casablanca+and+Dublin (morgan_orange, 14:01:04)
    13. 53 JIRAs have been created to address versioning issues detected by Sylvain (morgan_orange, 14:01:38)
    14. in link with discussion with OOM team (morgan_orange, 14:01:49)
    15. Yang asks for the overall saving from Casablanca (morgan_orange, 14:02:04)
    16. we need to sum the column, when the docker building is already well designed, migrating will not save lots of place but if not cleaning of build resources not used at runtime mays save lots of time) (morgan_orange, 14:03:00)
    17. first feedback from windriver (morgan_orange, 14:03:40)
    18. shortage of resources => we need more more RAM (morgan_orange, 14:03:56)
    19. Dmitry indicates that CSIT are using docker-compose which reference non official docker images (wurstmeister -> more or less under controlled), atmoz/sftp (use/case/5G-bulkpm) not official, no guarantee that it is maintained (morgan_orange, 14:07:03)
    20. lots of deprecated versions used in CSIT tests (morgan_orange, 14:08:24)
    21. gwu mentions that CSIT are not part of the release, images may not be managed the same way => CSIT tests used for testing (mock server, utilities) (morgan_orange, 14:09:57)
    22. CSIT requirements could be modified (support arm?), component teams are responsible of their CSIT tests/dockers/.. (morgan_orange, 14:11:21)


Meeting ended at 14:12:55 UTC (full logs).

Action items

  1. (none)


People present (lines said)

  1. morgan_orange (31)
  2. gwu (10)
  3. collabot (4)


Generated by MeetBot 0.1.4.