#onap-int: Integration Weekly
Meeting started by gwu at 13:03:13 UTC
(full logs).
Meeting summary
-
- thanks to everyone for hard work and
dedication; integration is done with Dublin release (gwu,
13:04:12)
- expect TSC to approve the release
tomorrow (gwu,
13:04:24)
- s3p test results were good; most issues were
environmental stability (gwu,
13:06:01)
- will request TSC to add more resources to the
wind river lab: more RAM and CPUs (gwu,
13:06:55)
- any remaining dublin issues (gwu, 13:07:20)
- issues with SDNC UEB listener on oom master
branch (gwu,
13:08:39)
- wiki page on CI testing (gwu, 13:11:36)
- 3 follow up items from last week: (gwu,
13:11:51)
- Brian has a video on testing (gwu,
13:12:06)
- Morgan release notes or wiki on the CI testing
chain (gwu,
13:12:31)
- Yang already well referenced the postman
collection, it is enough for the release (morgan_orange,
13:12:59)
- CI/CD "don't break the build" priority for El
Alto (gwu,
13:13:05)
- lab capacity planning (gwu, 13:13:26)
- some rules are needed to garantee resources for
integration team (and avoid being stuck few days before the
release) (morgan_orange,
13:14:00)
- a cap shall be defined per project (50 Go? too
small...) to motivate using shared resources when possible..
(morgan_orange,
13:15:05)
- proposed 50 GB RAM limit per project tenant;
teams to share ONAP instances where full ONAP is required
(gwu,
13:15:12)
- afenner: maybe there could be a way to tell if
an ONAP instance is still being used, so we don't have unused ONAP
instances taking up space (gwu,
13:18:46)
- wind river currently has about 5 TB of RAM,
each instance of ONAP takes about 250 GB of RAM (gwu,
13:22:23)
- morgan: ONAP at 250 GB seems to take too much
RAM for the functionality it provides; maybe TSC can consider this
as well (gwu,
13:26:32)
- are all ONAP components required? we should
identify exact list of components required for each use case
(gwu,
13:30:04)
- ONAP CPU usage is also something to review;
ONAP idle CPU consumption is too high; some pods are at 100% CPU all
the time (gwu,
13:30:45)
- Brian started to establish a link between the
tests / use cases and pods. There are more than 250 pods and 61
robot healthcheck + use cases. It seems that some pods are simply
not used. (morgan_orange,
13:31:43)
- ACTION: yang create a
story to follow-up on real resource usage in ONAP and see if it can
be reduced (morgan_orange,
13:32:20)
- cost for Orange Lab RAM upgrade: 36K$ for 52x32
Go (Dell and Huawei) (morgan_orange,
13:37:33)
- probably one of the main issue: people start
VMs and just forget to clean them (morgan_orange,
13:43:34)
- better visibility and garbarge collector
mechanism could be useful (morgan_orange,
13:43:59)
- El Alto priorities (gwu, 13:44:55)
- the variety of CI systems for ONAP is hard for
newbies to understand (gwu,
13:52:33)
- Jim Baker sharing El Alto roadmap (morgan_orange,
13:54:19)
- https://wiki.onap.org/display/DW/Release+Planning
(morgan_orange,
13:54:24)
- Jim reminds us of Aug 12 early drop (full
component release) date for El Alto (gwu,
13:54:26)
- Lasse has a question on jenkins job for
CIST (morgan_orange,
13:56:50)
- who is responsible for the jenkins sandbox? see
question on rocketchat (morgan_orange,
13:57:25)
- new LF ticketing system at
support.linuxfoundation.org (gwu,
14:00:13)
Meeting ended at 14:04:15 UTC
(full logs).
Action items
- yang create a story to follow-up on real resource usage in ONAP and see if it can be reduced
People present (lines said)
- gwu (24)
- morgan_orange (12)
- collabot` (3)
Generated by MeetBot 0.1.4.