#onap-int: Integration Weekly
Meeting started by gwu at 13:03:35 UTC
(full logs).
Meeting summary
- Updates (gwu, 13:06:50)
- El Alto early drop dates; testing start early
next week; teams provide images aug 5th (gwu,
13:08:13)
- early drop deliver by aug 19th; need to finish
testing by then (gwu,
13:09:24)
- sep 30 main el alto release; two more test
cycles after early drop (gwu,
13:10:16)
- need to discuss with oom team on how to manage
master vs staging given the current broken state (gwu,
13:14:33)
- first need to re-regression test all the robot
scripts given the recent testsuite tests (gwu,
13:17:43)
- lab resource updates: set 80 GB RAM quota per
tenant (gwu,
13:18:24)
- some time spent reinstalling SB04 due to lab
hardware issues (gwu,
13:19:54)
- PTL election (gwu, 13:23:08)
- Yang will step down as PTL; please send in your
self-nominations for Integration PTL (gwu,
13:23:36)
- Premerge verification process (gwu, 13:26:55)
- Premerge verification INT-1153 (gwu,
13:27:05)
- China Telecom Performance benchmark (gwu, 13:31:58)
- issues were encountered deploying ONAP dublin
on bare metal; help requested (gwu,
13:33:26)
- benchmark test schedule shared with the
team (gwu,
13:34:37)
- SDC updates (gwu, 13:36:06)
- SDC frankfurt to consolidate a 4 SDC roles into
one (gwu,
13:37:32)
- other (gwu, 13:51:38)
- Yang an d Gary have new email addresses
(gwu,
13:51:56)
- Yang: xuyang11@gmail.com (gwu,
13:52:08)
- Gary: gary.wu@gmail.com (gwu,
13:52:19)
- email for PTL self-nomination will be sent
later today (gwu,
13:56:50)
Meeting ended at 13:57:04 UTC
(full logs).
Action items
- (none)
People present (lines said)
- gwu (25)
- collabot` (3)
Generated by MeetBot 0.1.4.