    1. bob monkman (bob_monkman, 14:57:25)
    2. Joe Kidder (joekidder_, 14:57:35)
    3. Stan Kardach (StanKardach_mobi, 14:58:18)
    4. Vijayendra Radhakrishna (Vijayendra, 14:58:32)
    5. Alexandru Avadanii (Enea) (AlexAvadanii, 14:59:26)
    6. Florin DUmitrascu (florind, 15:00:40)
    7. Josep Puigdemont (joseppc, 15:04:38)
    8. Fuel Deployment Status (bob_monkman, 15:10:45)
    9. Fuel 8 in the middle of deploying Openstack (bob_monkman, 15:11:07)
    10. can provision the nodes with minor issues, cleanly (bob_monkman, 15:11:29)
    11. there is a stability issue with one of the compute nodes (bob_monkman, 15:11:59)
    12. still working with a 3 node system for the Fuel Deployment test (bob_monkman, 15:14:17)
    13. getting ready to move to a 5 node HA from the previous Arno Functest Pod (bob_monkman, 15:15:12)
    14. have decided to consolidate all changes to Fuel and related modules in our own repo to a single big gerrit review (bob_monkman, 15:17:45)
    15. syncing with stable release 8 of Fuel during this phase (bob_monkman, 15:18:15)
    16. the Be release of ODL still has x86 dependencies and manual changes were required to automate these changes to compile the library (bob_monkman, 15:20:52)
    17. still working through OpenStack integration with Fuel and we are still discovering mostly minor issues as we go. (bob_monkman, 15:23:09)
    18. the changes from Fuel 7 to Fuel 8 were bigger than expected. (bob_monkman, 15:24:21)
    19. even though we have been running the Functest on Arno level components, we expect little diference in running the same test on B-release components (bob_monkman, 15:32:01)
    20. discussion of the the scenarios we will need to run (bob_monkman, 15:37:05)
    21. we will test 3 scenarios only- nosdn-nofeature, odl- l2-ha, odl-l3-ha (bob_monkman, 15:38:40)
    22. we have an unknown wrt the vIMS Clearwater (bob_monkman, 15:39:13)
    23. OK...so we are close on deployment and have a reasonable chance to finish before 20 March (bob_monkman, 15:45:19)
    24. then we will be ready for final Functest runs and documentation. (bob_monkman, 15:46:54)


Meeting ended at 15:47:04 UTC (full logs).

Action items

  1. (none)


People present (lines said)

  1. bob_monkman (21)
  2. collabot` (3)
  3. joekidder_ (3)
  4. joseppc (2)
  5. StanKardach_mobi (2)
  6. florind (1)
  7. Vijayendra (1)
  8. AlexAvadanii (1)