#opnfv-meeting: Second Arno adjusted target release plan planning meeting :D
Meeting started by ChrisPriceAB at 07:01:49 UTC
(full logs).
Meeting summary
- roll call (ChrisPriceAB, 07:01:55)
- Uli (ulik,
07:02:06)
- Release readiness update (ChrisPriceAB, 07:04:07)
- https://wiki.opnfv.org/releases/arno/releasereadiness
release readiness task list (ChrisPriceAB,
07:04:25)
- we discussed last night beginning to put
dependancies in this task list, I also had an action to update the
opnfvdocs pieces. (ChrisPriceAB,
07:04:49)
- these did not start last night after the
meeting, we can do so today. (ChrisPriceAB,
07:05:03)
- we agreed to use "themes" as a way or
organising activities into dependancies, rather than trying ot use
the numbered list. (ChrisPriceAB,
07:05:36)
- Frank Brockners (frankbrockners,
07:05:54)
- we also agreed to provide some project planning
on the wiki and develop that during today. (ChrisPriceAB,
07:06:14)
- Themes = high-level categories/groups
(frankbrockners,
07:06:29)
- have a look at the wiki (frankbrockners,
07:06:39)
- The themes we to be idetifyable activities that
might contain sub-tasks that are easily refferable as depenadancies
on the other items (like a story) (ChrisPriceAB,
07:07:03)
- first column is the category - things that
naturally belong together (frankbrockners,
07:07:08)
- a theme is like SYS.READY which requires all
system readiness activities to be complete prior to the theme itself
being ready (ChrisPriceAB,
07:07:40)
- we additional articulated the task dependancy
that forms the process required to achieve Arno completion
(ChrisPriceAB,
07:08:48)
- Time to release readiness: max{TEST.READY,
SYS.READY} + max{SYS.AUTOMATED,TEST.EXEC} + SYS.RELEASE +
DOCS.READY (ChrisPriceAB,
07:08:51)
- this provides us with a way of combining tasks
and pending time into an equation that gives an indicative release
date (ChrisPriceAB,
07:09:26)
- we still have not begun to work with functest,
morgan is back in the office today. (ChrisPriceAB,
07:10:42)
- and there are themes/categories which have an
"unknown" time for now - true for SYS.RELEASE, SYS.READY and
TEST.READY (frankbrockners,
07:11:33)
- in parallel jose_lausuch will work on Tempest
automation, pbandzi will work on robot automation, the app deploy
teams are working in parallel. (ChrisPriceAB,
07:11:38)
- no timelines have been developed for these
activities yet. (ChrisPriceAB,
07:11:50)
- ACTION: all project
leads to ensure we have time estimates for remaining tasks and that
the dependancies are defined on other tasks (ChrisPriceAB,
07:12:45)
- this will provide a method of estimating
parallelism and the critical path for the remaining project
activities (ChrisPriceAB,
07:13:11)
- we need to work in parallel on the WiKi during
the day and will agree between the project leads on the final
pre-TSC meeting today on the proposed plan (ChrisPriceAB,
07:14:28)
- activities to be completed prior to Final pre-TSC Arno planning meeting. (ChrisPriceAB, 07:20:31)
- fill in column 7 (dependancies) where needed to
be drawn out (ChrisPriceAB,
07:21:05)
- fill in column 6 (time to completion) with
estimates on task completion timelines (ChrisPriceAB,
07:21:27)
- only add dependancies were there cannot be
parallelism (that includes resources) (ChrisPriceAB,
07:21:50)
- for tasks "almost complete" where we will be
troubleshooting when a dependant task tries to use it, it may be
better to dfactor that cost in to the dependant task.
opinions? (ChrisPriceAB,
07:22:39)
- ACTION: functest team
to complete the project with best known estimates (ChrisPriceAB,
07:23:28)
- ACTION: opnfvdocs
team to compete actions outlined in the previous meeting
(ChrisPriceAB,
07:23:45)
- ACTION: PL's to work
on the project plan text on the wiki. We can add a description of
our tasks in simple language there which we can edit after lunch
today into a singular Arno text (ChrisPriceAB,
07:24:39)
Meeting ended at 07:26:52 UTC
(full logs).
Action items
- all project leads to ensure we have time estimates for remaining tasks and that the dependancies are defined on other tasks
- functest team to complete the project with best known estimates
- opnfvdocs team to compete actions outlined in the previous meeting
- PL's to work on the project plan text on the wiki. We can add a description of our tasks in simple language there which we can edit after lunch today into a singular Arno text
People present (lines said)
- ChrisPriceAB (51)
- ulik (14)
- frankbrockners (11)
- collabot (3)
Generated by MeetBot 0.1.4.