#opnfv-meeting: TSC Meeting
Meeting started by ChrisPriceAB at 13:59:25 UTC
(full logs).
Meeting summary
- Roll Call (ChrisPriceAB, 13:59:31)
- Uli Kleber (uli-k,
13:59:36)
- Chris Price (ChrisPriceAB,
13:59:38)
- peter bandzi (on behalf of Frank
Brockners) (pbandzi_,
14:00:09)
- David Duffey (dduffey,
14:00:22)
- chenshuai (chenshuai,
14:00:23)
- Wenjing Chu (Wenjing,
14:00:24)
- Dan Radez (radez,
14:00:28)
- Tapio Tallgren (Tapio_T,
14:01:41)
- Gerald Kunzmann (proxy for DOCOMO) (GeraldK,
14:01:43)
- Agenda Bashing (ChrisPriceAB, 14:02:22)
- https://wiki.opnfv.org/wiki/tsc
TSC Agenda (ChrisPriceAB,
14:02:34)
- Armband to be added to the creation review
list (ChrisPriceAB,
14:04:31)
- LF pod discussion to be added, extra router
need (ChrisPriceAB,
14:05:03)
- Uli raises the topic of running CI and the
community labs, including needed support for Pharos. (ChrisPriceAB,
14:05:51)
- Upcoming OPNFV elections (ChrisPriceAB, 14:06:38)
- Dave Neary (proxy for Chris Wright)
(dneary,
14:07:13)
- Dirk Kutscher (dku,
14:07:54)
- goal is to have TSC chair and committers
elected before board elections (GeraldK,
14:08:00)
- Bryan Sullivan (bryan_att,
14:08:13)
- Julien (julien_ZTE,
14:08:18)
- nominations for TSC and committer board member
starting from today (GeraldK,
14:08:46)
- http://lists.opnfv.org/pipermail/opnfv-tsc/2015-August/001229.html
(rpaik,
14:09:10)
- first election is for TSC chair open for all
TSC members (GeraldK,
14:10:14)
- second election if for a committer board member
open for all current OPNFV committers (GeraldK,
14:10:40)
- Uli proposed to have discussion on
wish-candidate for committer board member (GeraldK,
14:12:09)
- Uli mentions original intention of that
committer member in the board was to bring more technical opinion to
the board (GeraldK,
14:13:32)
- ACTION: ChrisPriceAB
to set a slice in the tech discuss call to discuss the committer
election. (ChrisPriceAB,
14:15:12)
- OPNFV design summit in November (ChrisPriceAB, 14:16:04)
- Summit planning is final, and speakers have
been notified (dneary,
14:17:23)
- http://events.linuxfoundation.org/events/opnfv-summit/program/schedule
OPNFV Summit program (ChrisPriceAB,
14:17:45)
- https://etherpad.opnfv.org/p/OPNFV_Design_Summit_2015
(HKirksey,
14:17:57)
- https://etherpad.opnfv.org/p/OPNFV_Design_Summit_2015
OPNFV Design summit planning ethepad (ChrisPriceAB,
14:18:00)
- Some talks were moved to the Design Summit
which is in early stages now (dneary,
14:18:07)
- Additional sessions can be proposed to the
design summit (ChrisPriceAB,
14:18:59)
- ODP & OpenDaylight will also co-locate
their hackfests during the OPNFV Design Summit in November
(rpaik,
14:19:09)
- the design summit will be colocated with the
OpenDaylight design summit (ChrisPriceAB,
14:19:12)
- the design summit will additionally play host
to an ODP summit on the second day. (ChrisPriceAB,
14:20:13)
- Chanchai proposes a discussion on the topic of
carrier grade (ChrisPriceAB,
14:20:38)
- TSC 2016 Events Schedule (ChrisPriceAB, 14:22:26)
- Talk slots will be 20 minutes, panels 40
minutes, and labs 60 minutes; session chairs will crack the whip for
time-keeping (dneary,
14:22:35)
- initial proposals for the 4 planned design
summit events for 2016 are: (ChrisPriceAB,
14:23:27)
- At the LinuxFoundation collaboration summit in
California in March (ChrisPriceAB,
14:23:42)
- At the OPNFV Summit in Europe in June
(ChrisPriceAB,
14:24:37)
- At the orange sillicon valley campus in
California in Q3 prior to the C-Release (ChrisPriceAB,
14:25:22)
- At LinuxCon Europe in October (ChrisPriceAB,
14:25:34)
- ask for email with dates of proposed hackfest
schedule (RayNugent_,
14:30:07)
- LF DC discussion, sourcing another router to reduce downtime (ChrisPriceAB, 14:30:29)
- there is a need for additional vlans in the DC
due to our repurposing of the DC. Adding vlans affects services,
installing a router for OPNFV will reduce our coupling to the
infrastructure (ChrisPriceAB,
14:31:20)
- additional router will cost ~$1500 (rpaik,
14:31:44)
- adding a router will cost around $1,500
USD (ChrisPriceAB,
14:31:48)
- VOTE: Voted on "Shall
the TSC allocate approximately $1500 USD to purchase a router for
the lab?" Results are, +1: 10 (ChrisPriceAB,
14:33:05)
- Weekly Brahmaputra release project meeting (ChrisPriceAB, 14:34:24)
- Debra will run the first Brahmaputra planning
meeting after the TSC call and will begin work on setting milestone
C planning (ChrisPriceAB,
14:35:09)
- Project creationg review for the SDNVPN project (ChrisPriceAB, 14:36:19)
- https://wiki.opnfv.org/sdnvpn
project proposal (ChrisPriceAB,
14:36:25)
- Tim outlines the project intends to address
extending VPN's in the datacenter (ChrisPriceAB,
14:36:53)
- Tim describes that there is background work in
various upstream projects and that the time is right to begin the
project in OPNFV (ChrisPriceAB,
14:37:54)
- the committer list is not up to date at this
time. (ChrisPriceAB,
14:38:07)
- uli-k asks if we should consider all
controllers in this project? (ChrisPriceAB,
14:39:50)
- Tim responds that it depends on contribution
into the project. Adding other controllers should be
achievable. (ChrisPriceAB,
14:40:15)
- clarification on the described scope of the
project: The project will be done in collaboration with the related
bgpvpn project in OpenStack and supported implementations in SDN
controllers to make sure that the functionality can be integrated on
the OPNFV reference platform for the Brahmaputra release and
onwards. (ChrisPriceAB,
14:41:53)
- a question was raised if this project will
develop code upstream, tim responds that developers from many
upstream projects are involved in the OPNFV project (ChrisPriceAB,
14:43:54)
- dlenrow (dlenrow,
14:44:24)
- VOTE: Voted on "Vote to
create the SDNVPN project?" Results are, +1: 12 (ChrisPriceAB,
14:46:46)
- proxy for Wenjing (rpaik,
14:46:50)
- Creation review of the Controller Performance Testing project (ChrisPriceAB, 14:47:24)
- https://wiki.opnfv.org/project_proposals/cperf
Controller Performance Testing proposal (ChrisPriceAB,
14:47:49)
- Dan outlines a desire to establish a project
that performs performance testing of controllers in real hardware
deployments for SDN controllers (ChrisPriceAB,
14:48:35)
- there will be participation from the upastream
ODL performance testing project (ChrisPriceAB,
14:48:59)
- the team explicitly intends to work with
academic and standards groups (ChrisPriceAB,
14:49:17)
- the team additionally hopes to work with other
SDN controller teams in this project (ChrisPriceAB,
14:50:32)
- the question is posed if OVN is in this scope,
dan responds that OVN is not currently in scope and implements a
different architecture which may make it challenging (ChrisPriceAB,
14:51:35)
- proxy for Wenjing (rpaik,
14:53:48)
- VOTE: Voted on "Vote to
create the controller performance testing project?" Results are, 0:
2, +1: 9 (ChrisPriceAB,
14:53:58)
- Creation review of the dovetail project. (ChrisPriceAB, 14:54:24)
- https://wiki.opnfv.org/project_proposals/opnfv_compliance
dovetail proposal (ChrisPriceAB,
14:54:34)
- chrispriceab outlines the proposal and there
were no further questions. (ChrisPriceAB,
14:57:04)
- proxy for Wenjing (rpaik,
14:57:52)
- VOTE: Voted on "Vote to
create the dovetail project?" Results are, +1: 13 (ChrisPriceAB,
14:58:02)
Meeting ended at 15:00:45 UTC
(full logs).
Action items
- ChrisPriceAB to set a slice in the tech discuss call to discuss the committer election.
Action items, by person
- ChrisPriceAB
- ChrisPriceAB to set a slice in the tech discuss call to discuss the committer election.
People present (lines said)
- ChrisPriceAB (66)
- collabot (25)
- dneary (18)
- GeraldK (13)
- rpaik (11)
- TomNadeau (10)
- bryan_att (10)
- uli-k (6)
- dlenrow (5)
- julien_ZTE (5)
- pbandzi_ (5)
- bjskerry (3)
- AndreaP (3)
- Tapio_T_ (3)
- HKirksey (3)
- dku (3)
- Tapio_T (2)
- Wenjing (2)
- ramki (2)
- radez (1)
- RayNugent_ (1)
- chenshuai (1)
- dduffey (1)
- VikramDham (1)
- ildikov (1)
Generated by MeetBot 0.1.4.