#opnfv-release: OPNFV release

Meeting started by dmcbride_ at 15:01:27 UTC (full logs).

Meeting summary

  1. roll call (dmcbride_, 15:02:15)
    1. David McBride (dmcbride_, 15:02:24)
    2. TIm Rozet (trozet, 15:02:25)
    3. Justin (chigang_, 15:02:34)
    4. Ross Brattain (rbbratta, 15:02:44)
    5. Ray Paik (rpaik, 15:03:17)
    6. Mark Beierl (mbeierl, 15:04:07)
    7. Cristina Pauna (CristinaPauna, 15:04:36)

  2. schedule review (dmcbride_, 15:08:37)
    1. efoley (efoley, 15:08:57)
    2. MS3.0 completed successfully on Friday, Dec 15 (dmcbride_, 15:10:11)
    3. Euphrates 5.1 release completed successfully on Friday, Dec 15. Download page went live on Dec 18. (dmcbride_, 15:10:39)
    4. MS4 (test framework ready) - Jan 12 (dmcbride_, 15:12:01)
    5. MS3.1 (pass health check for nosdn / nofeature scenario) - Jan 15 (dmcbride_, 15:14:57)
    6. Cedric proposes adding api connection test to the requirements for MS3.0 (dmcbride_, 15:20:53)
    7. Cedric is evaluating methods for verifying openstack version (dmcbride_, 15:21:27)
    8. trozet and CristinaPauna concur on additional requirement for MS3.0 (dmcbride_, 15:21:54)
    9. MS3.2 (deploy sdn scenario and pass health check) - Feb 02 (dmcbride_, 15:22:46)
    10. https://jira.opnfv.org/browse/FUNCTEST-806 (ollivier, 15:23:03)
    11. https://git.opnfv.org/functest/tree/functest/ci/testcases.yaml#n12 (ollivier, 15:23:18)
    12. dmcbride will be tracking installer status on a weekly basis (dmcbride_, 15:28:22)

  3. MS4 compliance (dmcbride_, 15:30:11)
    1. goal of MS4 is to make sure that test frameworks are ready for use by feature projects (dmcbride_, 15:32:13)
    2. MS4 applies to functest, yardstick, vsperf, storperf, and bottlenecks (dmcbride_, 15:33:03)
    3. https://build.opnfv.org/ci/view/storperf/job/storperf-verify-master/ (mbeierl, 15:39:10)
    4. ollivier makes the point that test frameworks should verify compliance with MS4 through unit tests (dmcbride_, 15:40:04)
    5. functional gating could be implemented using saved apex images that are known to have passed previous runs of functest (dmcbride_, 15:45:29)

  4. release meeting through the end of year holidays (dmcbride_, 15:51:31)
    1. meeting cancelled for Dec 26 (dmcbride_, 15:51:50)
    2. next meeting on Jan 02 (dmcbride_, 15:52:01)


Meeting ended at 15:52:13 UTC (full logs).

Action items

  1. (none)


People present (lines said)

  1. dmcbride_ (23)
  2. mbeierl (4)
  3. collabot (3)
  4. ollivier (2)
  5. chigang_ (2)
  6. trozet (2)
  7. rpaik (2)
  8. efoley (1)
  9. rbbratta (1)
  10. CristinaPauna (1)