#acumos-meeting: Acumos TSC Meeting
Meeting started by bryan_att at 13:02:39 UTC
(full logs).
Meeting summary
- Agenda (bryan_att, 13:02:54)
- TSC roll call: Ofer, Jack, Zhengyuxuan,
Pantelis, Nat (bryan_att,
13:05:02)
- Last week's minutes were approved (bryan_att,
13:05:38)
- Bryan Sullivan (bryan_att,
13:05:47)
- Nat: add topics on update of the LF instance,
and adding committer for the Azure client repo (bryan_att,
13:06:57)
- Jack: adding to the agenda the creation of a
policy for attendance (or named alternative) (bryan_att,
13:07:48)
- Status of open items (bryan_att, 13:08:41)
- Strategic Positioning (Pantelis) (bryan_att, 13:12:31)
- Pantelis: Isee the recently developed support
for kubernetes as a good thing, with opportunities to disaggregate
the platform; this item can be taken off the standing agenda as
there is now progress. (bryan_att,
13:14:06)
- Jack: re the potential relationship with TIP,
who is involved in TIP that can track this? (bryan_att,
13:14:40)
- Pantelis and Ofer will investigate and report
to the TSC (bryan_att,
13:15:39)
- LF Marketplace refresh (bryan_att, 13:15:59)
- Nat: looking for standing 2 or 4 week upgrade
cycle; have May 10 installed, and ready to deploy June 11
(bryan_att,
13:16:59)
- Jack: this should be in scope for automated
deployment under CI/CD; the options (e.g. from master or a branch)
need to be worked out (bryan_att,
13:18:26)
- Nat: for now, propose once every 4 weeks with
tests on the staging server, and important maint updates as
needed (bryan_att,
13:19:19)
- Vanessa: is the staging env a mirror of
production (typically is) ? (bryan_att,
13:20:07)
- Nat: it isn't identical but pretty close
(bryan_att,
13:20:57)
- Jack: Vanessa and LF team can deploy emergency
fixes as needed (bryan_att,
13:23:54)
- TSC agrees to the 4-week update cycle
(bryan_att,
13:24:22)
- Sachin: need a dedicated main window for
updating the production instance (bryan_att,
13:25:07)
- Vanessa: 8PM Eastern time is recommended
(bryan_att,
13:26:36)
- the TSC agreed to the schedule for the main
window (bryan_att,
13:27:19)
- Subcommittee reports (bryan_att, 13:27:35)
- Ofer the Community commiittee is making
progress, all items are in Jira (bryan_att,
13:28:35)
- Jack: is the community aware of how to find the
reqs and submit their input? we will be closing the req window next
week. (bryan_att,
13:30:24)
- Jack: following that the Arch committee will
consider it; but we also need to identify which resources will drive
the development (bryan_att,
13:31:34)
- Jack: M2 will probably be extended to allow the
Arch committee to discuss the items (bryan_att,
13:32:21)
- Pantelis: have some questions about the use of
Jira, and how projects define scrums (bryan_att,
13:33:38)
- Vanessa: other projects typically do have their
own sub-project (project, repo) structure in Jira so they can plan
scrums etc (bryan_att,
13:34:58)
- Jack: recommend that we enable the PTLs and
projects to use those features (bryan_att,
13:36:33)
- Bryan: this is typical in other projects, but
there will be some effort to migrate the existing issues into
projects (bryan_att,
13:38:32)
- Jack: how do cross-project epics fit this
plan? (bryan_att,
13:39:56)
- Vanessa: we cold keep them at the "Acumos"
project as the umbrella (bryan_att,
13:40:22)
- Jack: the question is what do we need to change
now? (bryan_att,
13:45:46)
- Vanessa: recommend we make changes now
(bryan_att,
13:46:12)
- Anwar: we discussed in the Arch call that to
support agile, we need cross-project sprints defined in the
development timeline; the Arch team recommended that we define the
common sprint schedule now (bryan_att,
13:47:29)
- Anwar: as a product there needs to be
coordinated sprints between the component projects (bryan_att,
13:48:18)
- Vanessa: we can also create scrum boards
filtered for components (bryan_att,
13:48:58)
- Jack: so we could use the current
structure (bryan_att,
13:49:31)
- Anwar: will work with Pantelis to drive the
scrum board implementation using the current Jira structure
(bryan_att,
13:51:00)
- Arch committee (bryan_att, 13:51:07)
- Anwar: current reqs have been reviewed, input
on priority is being collected, next is to determine which can be
delivered based upon resources (bryan_att,
13:51:58)
- Anwar: we also need to ensure the test team has
a platform to test during the dev cycle, so factor that into the
planning (bryan_att,
13:53:08)
- Anwar: we also need the input/support of the
release manager (when that role has been filled) (bryan_att,
13:53:42)
- Jack: we really need someone to step up to
support the release manager role (bryan_att,
13:54:25)
- New Items (bryan_att, 13:54:37)
- Jack: we need a release manager volunteer to be
very available and proactive (bryan_att,
13:55:02)
- Jack: we have several projects without PTLs;
looking for volunteers (bryan_att,
13:56:27)
- Jira Admin Rights (bryan_att, 13:56:52)
- Scott: TSC needs to determine who has Jira
Admin rights; we are talking about rights to customize Jira
(bryan_att,
13:58:03)
- Scott: also approval of new committers e.g.
Phillipe as PTL of Onboarding wants to take on the role of
committer (bryan_att,
13:58:54)
- TSC agreed for Phillipe as committer
(bryan_att,
13:59:57)
- Nat: also need Santosh to be added to the other
deploy repos as committer, for the deployment project (bryan_att,
14:01:06)
- Vanessa: re Jira admin, this is at the project
level only not overall, and that needs to be approved by the
TSC (bryan_att,
14:01:50)
- Jack: get the names on the agenda for next
week, or via email (bryan_att,
14:02:57)
- Vanessa: we could also use the IRC bot to
record the votes on IRC (bryan_att,
14:03:53)
Meeting ended at 14:04:21 UTC
(full logs).
Action items
- (none)
People present (lines said)
- bryan_att (59)
- collabot_ (3)
Generated by MeetBot 0.1.4.