#fdio-csit: CSIT Project Meeting

Meeting started by mackonstan at 15:05:37 UTC (full logs).

Meeting summary

    1. Jan Gelety (jgelety, 15:05:39)
    2. Tibor Frank (tifrank, 15:05:41)
    3. Juraj Linkeš (jlinkes, 15:05:42)

  1. Agenda bashing (mackonstan, 15:05:50)
    1. Vratko Polak. (vrpolak, 15:05:52)

  2. Inputs from projects - VPP (mackonstan, 15:06:12)
    1. Andrew, RC2 almost ready. (mackonstan, 15:06:35)

  3. Releases CSIT-2101 (mackonstan, 15:07:07)
    1. today is RC2 (mackonstan, 15:07:39)
    2. Tibor, many RC1 test dry runs executed (mackonstan, 15:07:57)
    3. Tibor, interim results in draft report version (mackonstan, 15:09:45)
    4. https://docs.fd.io/csit/master/report/vpp_performance_tests/packet_throughput_graphs/ip4.html (mackonstan, 15:09:48)
    5. Dave Wallace (dwallacelf, 15:09:58)
    6. Tibor, comparison tables are also being populated incl. 2009.0 retest (mackonstan, 15:11:15)
    7. Jan, Geneve tests still under review, addressing last comments (mackonstan, 15:12:07)
    8. Vratko, nat44ed throughput tests and ip6-rnd and ip4-rnd are under review (mackonstan, 15:12:50)
    9. Juraj, 2n-tx2 testbed is operational, all working. (mackonstan, 15:14:19)
    10. Tibor, report TODO email sent out. (mackonstan, 15:16:10)
    11. Maciek, Vratko: methodology needs to be updated for nat44ed throughput, ip4- and ip6-rnd testing. (mackonstan, 15:16:47)

  4. Releases CSIT-2009 (mackonstan, 15:17:48)
    1. Dave, v20.09.01 maintenance rls target 17-Feb. (mackonstan, 15:18:56)
    2. (correction) Davee, VPP v20.09.01 maintenance rls target 17-Feb (mackonstan, 15:19:25)

  5. Physical Infrastructure (mackonstan, 15:19:34)
  6. Physical Infrastructure - FD.io DC move in Jan/Feb 2021 and lab extension in 2021. (mackonstan, 15:31:34)
    1. (mackonstan, 15:31:46)
    2. Maciek, agreed on a call to ask Vexxhost about routing topology and packet forwarding between YUL1 and MTL1, assuming MTL2 is migrated in one step, stage-1 (mackonstan, 15:33:34)
    3. Maciek, agreed to set a move date for MTL2 for 11-Feb-2021, 1 day after report publish (mackonstan, 15:40:18)
    4. Maciek, re MTL1 (4 racks), balance the required work and strive to make the server move transparent to project operations (mackonstan, 15:45:19)
    5. Will produce draft proposals for MTL1 move, in the patch, review on the next week call (mackonstan, 15:47:13)
    6. https://gerrit.fd.io/r/c/csit/+/30662 (mackonstan, 15:47:23)

  7. Virtual Infrastructure, CI/CD (mackonstan, 15:47:39)
    1. Juraj, i40e dpdk driver, sporadic failures on arm and x86, created an entry in linux kernel bugzilla (mackonstan, 15:51:49)
    2. Maciek, opening the ticket in Intel IPS system to speed things up (mackonstan, 15:52:07)
    3. Juraj, q to Dave how is the Centos8 docker image generation going (mackonstan, 15:53:06)
    4. Dave, still a todo, hoping to make progress this week\ (mackonstan, 15:53:30)
    5. Dave, added more nomad monitors following outages on 4-/5-jan (mackonstan, 15:55:11)
    6. Dave, using WxT "jenkins-healthcheck" channel for monitoring results, as an interim (mackonstan, 15:57:39)
    7. Dave, propose to use the same ping monitor scripts for upcoming DC move (mackonstan, 15:58:24)
    8. Dave, jenkins parameterized work has been merged, going production soon (mackonstan, 15:59:29)


Meeting ended at 16:00:23 UTC (full logs).

Action items

  1. (none)


People present (lines said)

  1. mackonstan (37)
  2. collab-meetbot (4)
  3. jgelety (1)
  4. tifrank (1)
  5. jlinkes (1)
  6. vrpolak (1)
  7. dwallacelf (1)


Generated by MeetBot 0.1.4.