#onap-int: Integration weekly meeting 5/06/2019
Meeting started by morgan_orange at 13:02:16 UTC
(full logs).
Meeting summary
- call role (morgan_orange, 13:02:21)
- Yang (morgan_orange,
13:02:37)
- Morgan (morgan_orange,
13:02:43)
- akhila kishore (morgan_orange,
13:02:56)
- Andy Walshe (morgan_orange,
13:03:03)
- Gary (morgan_orange,
13:03:05)
- Lasse Kaihlavirta (morgan_orange,
13:03:14)
- liam Burke (morgan_orange,
13:03:18)
- Marco (morgan_orange,
13:03:21)
- Michal Ptacek (morgan_orange,
13:03:27)
- Rahul Tyagi (morgan_orange,
13:03:32)
- Tomas Levora (morgan_orange,
13:03:42)
- Mariusz Jablonski (morgan_orange,
13:03:50)
- Kenny (morgan_orange,
13:03:54)
- introduction (morgan_orange, 13:04:05)
- intensive testing in progress (morgan_orange,
13:04:28)
- RC2 was not announced as planned) (morgan_orange,
13:04:39)
- due to intensive testing, system becomes slower
triggering congestion and unexpected errors (morgan_orange,
13:05:06)
- most of the released image have been
provided (morgan_orange,
13:05:26)
- 2/3 of use cases (functional and non
functional) are completed (morgan_orange,
13:06:27)
- time to document properly the use case in
readthe docs (morgan_orange,
13:06:36)
- ACTION: all complete
readthedoc for the use case sections (morgan_orange,
13:06:53)
- test automation is also more than welcom
(morgan_orange,
13:07:03)
- Dublin Release Integration Testing Status (morgan_orange, 13:08:02)
- https://wiki.onap.org/display/DW/Dublin+Release+Integration+Testing+Status
(morgan_orange,
13:08:09)
- 5G - Configuration with NETCONF: work in
progress on windriver, could be hopefully completed this week
(morgan_orange,
13:09:46)
- critical outages on windriver on the 3rd of
June, reinstallation needed => could have impacted testing
teams (morgan_orange,
13:10:25)
- 5G PNF preonboarding => 1 part is finished,
other part in progress but no infor on the % of progress
(morgan_orange,
13:11:57)
- ACTION: yang sync
with 5G PNF preonboarding team (morgan_orange,
13:12:09)
- Scale Out (10): few issues raised over the
last days, fix expected soon especially on BPMN and OpenStack
adapter (manual workaround) - test on SB00 (morgan_orange,
13:14:03)
- workaround possible to update BPMN (replacing
jar file in SO) (morgan_orange,
13:14:39)
- CCVPN: lab migration in progress, the use case
could probably not be finalized for Dublin (morgan_orange,
13:15:35)
- Change Management - Flexible designer &
Orchestrator (13): blocked by portal issues (not available for
several hours) (morgan_orange,
13:16:33)
- from SDC to SO it is OK but problem in the BPMN
container (morgan_orange,
13:17:01)
- discussion on Portal issues (morgan_orange,
13:26:00)
- ETSI Alignment moved to El Alto (shoudl be
removed from the page) (morgan_orange,
13:29:12)
- CDS (25) closed to 100% (morgan_orange,
13:29:13)
- HPA us e case (12) is completed, (34) still in
progress (morgan_orange,
13:30:45)
- ACTION: Yang send a
mail to the people involved in Dublin use case wiki pages to update
the page (if not completed yet) (morgan_orange,
13:31:49)
- ACTION: Brian send a
mail to the people involved in Dublin use case wiki pages to update
the page (if not completed yet) (morgan_orange,
13:32:35)
- Dublin Release Integration Test Blocking Issues (morgan_orange, 13:33:55)
- https://wiki.onap.org/display/DW/Dublin+Release+Integration+Test+Blocking+Issues
(morgan_orange,
13:34:02)
- review of the bugs MULTICLOUD-660 could be
closed (sucessfully tested on OOM Gating last night) (morgan_orange,
13:40:11)
- SO-1869: Marco provided a fix => can be
closed (morgan_orange,
13:41:12)
- OOM-1851 => documentation needed for Dublin
(question dealing with this issue on the mailing list this
morning) (morgan_orange,
13:45:02)
- APPC-1613, as the use case seems OK, the jira
can probably be closed => to check with Lukasz (morgan_orange,
13:45:43)
- VNFSDK-407 => can be closed (gerrit_id
88730) (morgan_orange,
13:49:37)
- jira tickets with high severity should be
labbeled with integration at this stage (morgan_orange,
13:51:25)
- next week will be busy (DDF in
Stockholm) (morgan_orange,
13:55:41)
- AoB (morgan_orange, 13:56:18)
- question on a chat channel for integration
support (morgan_orange,
14:00:53)
- http://onap-integration.eastus.cloudapp.azure.com:3000/group/onap-integration
(morgan_orange,
14:01:11)
- question on the test procedure - tests done but
lots of changes seen in OOM, are we testing the target
release (morgan_orange,
14:01:54)
- tests done in integration lab usually based on
snapshot version, release versions seen in OOM corresponds to the
versions used for testing (morgan_orange,
14:02:36)
Meeting ended at 14:43:49 UTC
(full logs).
Action items
- all complete readthedoc for the use case sections
- yang sync with 5G PNF preonboarding team
- Yang send a mail to the people involved in Dublin use case wiki pages to update the page (if not completed yet)
- Brian send a mail to the people involved in Dublin use case wiki pages to update the page (if not completed yet)
People present (lines said)
- morgan_orange (57)
- collabot` (3)
Generated by MeetBot 0.1.4.