#onap-sdnc: SDNC Weekly 10/11/2017
Meeting started by mgkwill at 13:07:37 UTC
(full logs).
Meeting summary
- Release Milestones (mgkwill, 13:09:25)
- RC0 Milestone issues - Docs and
Versioning (mgkwill,
13:12:37)
- Other RC0 deliverables seem to be done
(mgkwill,
13:14:12)
- Jira Task Scrub (mgkwill, 13:14:21)
- Ecomp references in directed graph tasks still
being worked - JIRA SDNC-105 SDNC-106 - Dan doesn't think this issue
is breaking anything (mgkwill,
13:16:40)
- Dan walks through Independent Release
Versioning Task (mgkwill,
13:17:26)
- https://wiki.onap.org/display/DW/Independent+Versioning+and+Release+Process
(mgkwill,
13:17:55)
- Dan mentions version-manifest maven plugin that
helps verify no use of snapshots in pom.xml versions (mgkwill,
13:19:38)
- ACTION: Dan to clean
up SDNC backlog, as lots of tasks are done etc. (mgkwill,
13:20:01)
- RC0 Tasks (mgkwill, 13:21:10)
- Weekly Focus Areas twofold 1. Docs
Skeleton (mgkwill,
13:22:31)
- 2. Getting Rid of Snapshot Dependencies
(mgkwill,
13:26:53)
- ACTION: Marcus to get
rid of snapshot dependencies (mgkwill,
13:27:13)
- 3. Integration Blockers - Help will be
needed (mgkwill,
13:27:48)
- Dan goal is to turnaround any blockers from
integration within 24 hours. (mgkwill,
13:28:26)
- Services that use generic resource api - need
data, Dan created a container to test (mgkwill,
13:29:47)
- /2 to test UEB Listener (mgkwill,
13:30:37)
- R2 (mgkwill, 13:35:13)
- Focus for next release is carrier grade, but
Arch. Team figuring out what that means. (mgkwill,
13:35:40)
- Though no new use cases are supposed to be in
R2 - some new use cases like SD-WAN are being discussed.
(mgkwill,
13:36:58)
- Sharon mentions some carrier grade work they
are looking at for R2 and talks about other work that might fall
into new use case. (mgkwill,
13:38:33)
- ACTION: Sharon to add
work she talked about to SDNC backlog (mgkwill,
13:39:17)
- Disconnect As A Service is one of work items
Sharon mentioned, but agreement on it being self-contained.
(mgkwill,
13:40:04)
- We need to start building backlog for Beijing
(R2) (mgkwill,
13:40:53)
- Dan mentions that people should start adding to
the backlog - never too early (mgkwill,
13:41:38)
Meeting ended at 13:41:49 UTC
(full logs).
Action items
- Dan to clean up SDNC backlog, as lots of tasks are done etc.
- Marcus to get rid of snapshot dependencies
- Sharon to add work she talked about to SDNC backlog