- Feasibility of using the OVS QoS 'MaxRate' parameter to implement UNI Speed attribute (KLuehrs, 21:00:39)
- Confirmed OVS support MaxRate, QoS has been
added to OVS project and it has been merged. (KLuehrs,
21:06:34)
- ODL support for QoS - model has been updated.
No code exists yet. (KLuehrs,
21:07:08)
- Gabriel will check with QoS developer to learn
when code will be available. (KLuehrs,
21:08:27)
- When code is in OVSDB it should be fairly
simple to translate MaxRate to UNI Manager speed attribute.
(KLuehrs,
21:09:09)
- Unit Test Development techniques (KLuehrs, 21:09:46)
- We currently do not have resources available to
develop unit tests. The project may be able to get a waiver.
(KLuehrs,
21:11:51)
- Inocybe may be able to add some test classes
and some example functions to the UNI Manager code, to make it
easier for someone to follow. (KLuehrs,
21:12:26)
- OPNFV Brahamaputra release (KLuehrs, 21:13:35)
- OPNFV release team has asked about potential
conflicts with ODL karaf, e.g., Is the UNI-mgr karaf feature able
to run coexistent with the required karaf features used in OPNFV?
(do they collide with net-virt or sfc for instance or are they able
to run at the same time?) (KLuehrs,
21:44:43)
- Gabriel thinks the information they are looking
for is (1) What URLs and JSON payload does LSO API use when calling
ODL UNI Manager plug-in, and (2) is there, or is there potential
for, a port conflict between ODL karaf (8080, 8181) and Tomcat as
used by LSOAPI? (KLuehrs,
21:47:16)
- Currently our implementation of the OPNFV
LSOAPI uses port 9090 so there should be no conflict. (KLuehrs,
21:47:43)
- ACTION: Gabriel will
find out when ODL QoS implementation (code) will be done.
(KLuehrs,
21:48:27)
- ACTION: Inocybe will
create basic test framework for UNI Manager unit tests: test classes
and one or two sample functions for reference. (KLuehrs,
21:49:19)
- AGREED: Next week's
meeting (December 23) is cancelled due to holidays. The next UNI
Manager project meeting will be held at the regularly scheduled time
December 30. (KLuehrs,
21:51:24)
Meeting ended at 21:51:28 UTC
(full logs).
Action items
- Gabriel will find out when ODL QoS implementation (code) will be done.
- Inocybe will create basic test framework for UNI Manager unit tests: test classes and one or two sample functions for reference.